Phase 1 - Construction - 2001 Q3

[2001 Q1] [2001 Q2] 2001 Q3

  • 2001.07.02 - The forms for the driveway and front walkway are in place. The steel basement columns have arrived.
  • 2001.07.03 - Concrete poured for driveway and front walkway.



  • 2001.07.05 - Failed first electrical inspection: "More nail plates 2nd floor" is on the failure notice.
  • 2001.07.10 - Electrical inspection Passed - rough and service
  • 2001.07.11 - Framing inspection Passed - permit no. 01-392, Joe Hall; steel posts in basement installed; gas line trench
  • 2001.07.12 - Insulation batts arrived
  • 2001.07.13 - Insulation installation started; drywall materials arrived
  • 2001.07.16 - Curb pavers moved to match driveway
  • 2001.07.19 - Interior doors, trim arrived
  • 2001.07.20 - Drywall installation started



  • 2001.07.27 - Installation of interior doors, trim started



  • 2001.07.28 - Painting started



  • 2001.07.31 - Stair railings installed (not stained yet); hardwood floor in foyer installed; cabinets arrived
  • 2001.08.01 - Sidewalk forms in place; lockset on front door; underlayment placed in kitchen
  • 2001.08.02 - Sidewalk concrete poured; cabinet installation started; vinyl flooring in kitchen




  • 2001.08.06 - Exterior trim painted; still missing fypons over garage door and front door
  • 2001.08.07 - Air conditioner installed
  • 2001.08.09 - Plumbing fixtures installed
  • 2001.08.11 - Gutters installed



    Confirmed that sump pit will have wiring but no drainage outlet; would be installed with pump. Took pix of model house sump pump installation for future reference

  • 2001.08.16 - Concrete poured for driveway ramp
  • 2001.08.17 - Basement windows installed; thermostat installed
  • 2001.08.20 - Closet shelves and medicine cabinets installed?
  • 2001.08.21 - Electric meter installed
  • 2001.08.22 - Concrete patio in rear



  • 2001.08.23 - Submitted revised documents to Allied Mortgage
  • 2001.08.24 - Light fixtures installed; final millwork installed
  • 2001.08.26 - Electricity active
  • 2001.08.27 - Base price of Mercer model now $188K, $11K more than when I started
  • 2001.08.28 - Range hood installed - NOT BLACK; backyard stairs installed



  • 2001.08.29 - Carpeting installed!



  • 2001.08.30 - Stove and dishwasher arrived, installation started
  • 2001.08.31 - Gas meter installed
  • 2001.09.04 - Straw spread on soil



  • 2001.09.06 - Grass sod installed



  • 2001.09.09 - additional painting
  • 2001.09.10 - MORTGAGE LOCKED at 6.25% 3 pts.
  • 2001.09.12 - 1st walkthrough
  • 2001.09.14 - Home inspector walkthrough
  • 2001.09.21 - Washington Township issued Certificate of Occupancy
  • 2001.09.23 - Exterior shutters installed
  • 2001.09.24 - Settlement scheduled for 200109.28 1100
  • 2001.09.28 - SETTLEMENT