New home main page
Phase 1 - Construction - 2001 Q3
[2001 Q1] [2001 Q2] 2001 Q3
-
2001.07.02 - The forms for the driveway and front walkway
are in place. The steel basement columns have arrived.
-
2001.07.03 - Concrete poured for driveway and front
walkway.
-
2001.07.05 - Failed first electrical
inspection: "More nail plates 2nd
floor" is on the failure notice.
-
2001.07.10 - Electrical inspection Passed
- rough and service
-
2001.07.11 - Framing inspection Passed - permit
no. 01-392, Joe Hall; steel posts in basement
installed; gas line trench
-
2001.07.12 - Insulation batts arrived
-
2001.07.13 - Insulation installation started; drywall
materials arrived
-
2001.07.16 - Curb pavers moved to match driveway
-
2001.07.19 - Interior doors, trim arrived
-
2001.07.20 - Drywall installation started
-
2001.07.27 - Installation of interior doors, trim
started
-
2001.07.28 - Painting started
-
2001.07.31 - Stair railings installed (not stained yet);
hardwood floor in foyer installed; cabinets arrived
-
2001.08.01 - Sidewalk forms in place; lockset on front
door; underlayment placed in kitchen
-
2001.08.02 - Sidewalk concrete poured; cabinet
installation started; vinyl flooring in kitchen
-
2001.08.06 - Exterior trim painted; still missing fypons
over garage door and front door
-
2001.08.07 - Air conditioner installed
-
2001.08.09 - Plumbing fixtures installed
-
2001.08.11 - Gutters installed
Confirmed that sump pit will have wiring but no drainage
outlet; would be installed with pump. Took pix of model
house sump pump installation for future reference
-
2001.08.16 - Concrete poured for driveway ramp
-
2001.08.17 - Basement windows installed; thermostat
installed
-
2001.08.20 - Closet shelves and medicine cabinets
installed?
-
2001.08.21 - Electric meter installed
-
2001.08.22 - Concrete patio in rear
-
2001.08.23 - Submitted revised documents to Allied
Mortgage
-
2001.08.24 - Light fixtures installed; final millwork
installed
-
2001.08.26 - Electricity active
-
2001.08.27 - Base price of Mercer model now $188K, $11K
more than when I started
-
2001.08.28 - Range hood installed - NOT
BLACK; backyard stairs installed
-
2001.08.29 - Carpeting installed!
-
2001.08.30 - Stove and dishwasher arrived, installation
started
-
2001.08.31 - Gas meter installed
-
2001.09.04 - Straw spread on soil
-
2001.09.06 - Grass sod installed
-
2001.09.09 - additional painting
-
2001.09.10 - MORTGAGE LOCKED at 6.25% 3
pts.
-
2001.09.12 - 1st walkthrough
-
2001.09.14 - Home inspector walkthrough
-
2001.09.21 - Washington Township issued
Certificate of Occupancy
-
2001.09.23 - Exterior shutters installed
-
2001.09.24 - Settlement scheduled for 200109.28 1100
-
2001.09.28 - SETTLEMENT
New home main page
Phase 1 - Construction - 2001 Q3
[2001 Q1] [2001 Q2] 2001 Q3
Copyright © 2001, Mark Bersalona. All rights reserved.
|